We are heading into the last couple of months of the project and the interior of the buildings are mostly complete. The scaffolding has been removed and the landscaping work is progressing around site. The driveway is advancing well, with the exit ramp now in use.

The number of subcontractors on site will continue to decrease over the next month. This will mean less deliveries and fewer trucks causing traffic disruptions.

Unfortunately, we have had some security issues over the last month and now have a full-time guard based on site to monitor the building.

On Wednesday 17th November there will be some after-hours work, this will not be noisy works, as we will be completing the line marking of the driveway.