We receive regular updates from Wellington City Council about upcoming roadworks. The table below covers main Council scheduled roadworks for this month, in our local area. Note: dates may change due to weather or other unforeseen circumstances.
LOCATION | TYPE OF WORK | INDICATIVE DATES | TRAFFIC MANAGEMENT | OTHER |
Ngaio Gorge | Slip Stabilisation project | October 2020 to 2022 | Traffic reduced to one lane controlled traffic control | Further information on WCC website project page. |
Grant Road, Thorndon | Retaining walls strengthening project | Mid-February to early 2021 | Traffic reduced to one lane controlled by temporary traffic signals | |
Rangiora Avenue, Kaiwharawhara | Construction of new footpath and staircase down to Hutt Road. | July – August 2020 | Reduced parking during construction. Traffic controlled by stop go. Work hours 7am to 6pm Monday to Saturday. | Project delayed due to COVID-19 |
Latest updates on roadworks, road closures and events information can be found on the WCC website at: https://wellington.govt.nz/services/parking-and-roads/road-works/road-works-and-road-closures
A map of upcoming work for 2019/20 is at https://gis.wcc.govt.nz/LocalMaps/Viewer/?map=d322a03511294abcbe83a253b8700c02