Update – Bupa Care Home 122 Churchill Dr

Naylor Love have provided an update on September works at the 122 Churchill Drive site, which can be read in full by clicking here.

The structural steel for the entire building will be completed by the end of this month, concrete will continue to be poured throughout the remainder of the building. The fit-out work is gaining momentum as the building starts to be closed in, with the installation of the RAB board pre-clad system, windows, and roofing.

NL thank residents for  your understanding around the early pours throughout August, and during September there will be two pours commencing at 6:30am, planned for Friday 4 September, Wednesday 9 September, Thursday 10 September, Tuesday 29 September.

Questions are welcomed,  to e-mail on: katie.burley@naylorlove.co.nz